Artemis Gold Inc. is planning an upgrade for the current Blackwater Mine processing plant.

“The Phase 1A plans announced today will deliver a 33 per cent increase in plant capacity, at an industry leading capital intensity of less than $55 per annual tonne of throughput. The project will be funded out of operating cash flows, and the payback period is expected to be less than six months,” said Artemis Gold CEO Dale Andres.

“We expect Phase 1A to de-risk and enhance future free cash flows that are aimed at funding a larger Phase 2 expansion.”

The Company estimates Phase 1A will be completed at a capital cost of $100-$110 million.

Major mechanical equipment for this phase has been ordered, including a vertical mill to provide additional primary grinding capacity.

Construction work has also commenced with excavation of foundations in the plant area, while the concrete batch plant for the scope of work is being commissioned on-site.

The Company is continuing to progress the design and engineering for an optimized and accelerated Phase 2 expansion, including alternative methods for mine waste haulage.

The Blackwater Mine, roughly 160 kilometres southwest of Prince George, achieved its first gold and silver pour in January this year, and commercial production in May.

Something going on in the Nechako Valley area you think people should know about?
Send us a news tip by emailing pgnews@vistaradio.ca.

Darin Bain
Darin Bain
Darin is a news reporter for Vista Radio's Prince George stations. His career started in the Cariboo in 2020, working as a News Reporter in both 100 Mile House and Williams Lake before making the move to Prince George in late 2021.

Continue Reading

- Advertisement -

Related Articles

- Advertisement -

Latest News

B.C. Conservatives drop candidate over alleged online comments about Hitler

The B.C. Conservatives have dropped a second election candidate following allegations of antisemitic and racist social media posts.

Uniform Gang enforcement team launched for Northern B.C.

The Combined Forces Special Enforcement Unit of British Columbia (CFSEU-BC) announced the launch of its North District Uniform Gang Enforcement Team (UGET) in Prince George Today (Thursday).

B.C. leaders spar in fiery debate ahead of Oct. 24 election

B.C.’s three main party leaders clashed over affordability, health care and Indigenous rights in a heated televised election debate Wednesday evening.

Provincial election advance voting begins Friday

Final voting day for the provincial election is set for Oct. 24, but opportunities to cast your ballot early start this week.

B.C. NDP pledges millions for clean energy and climate programs

The B.C. NDP is promising millions of dollars in new investments in clean energy and climate programs if re-elected, while warning a Conservative government would roll back environmental protections. 
- Advertisement -